Mesh is alkali or E-glass fiber yarn woven by alkali-resistant polymer emulsion-coated fiberglass mesh products: GRC fiberglass mesh alkali, alkali-resistant wall enhancement, and mosaic Private Network tablets and stone, marble back paste mesh. Fiberglass mesh use described below:

1. The person responsible for the preparation of polymer mortar must be to ensure the quality of stirring.

2. The counter-clockwise rotation to open the lid, with a stirrer or other tools again stirred binder, the binder appears to avoid separation, stirring moderately, to avoid quality problems.

3. Polymer mortar mix ratio: KL Binder: 425 # sulfur cement: sand (with a 18 mesh sieve bottom): = 1: 1.88: 3.25 (weight ratio).

4. Cement, sand bucket, said after a good amount of iron into the gray tank for mixing, stir mix by adding a binder, stirring, stirring must be uniform to avoid segregation, was gruel. It may be appropriate to add water according to the workability.

5. Water concrete water.

6. Polymer mortar should be used with the distribution, polymer mortar preferably with a good run out within one hour. Polymer mortar should be in a cool place, avoid sun exposure.

7. A pre-required length, width, cut the mesh from the entire roll of fiberglass mesh, leaving the necessary lap length or length of the overlapping portion.

8. In the place clean, flat cut, cutting must be accurate, cut a good mesh must be rolled up, not allowed to fold, not allowed to stampede.

9. Do reinforcing layer Yang corner of the building, reinforcing layer shall be affixed to the inside of each side 150mm.

10. When applying the first pass mortar, EPS board should be kept dry, cotton board to remove harmful substances or impurities.

11. In polystyrene board scraping the surface with a layer of mortar, scraping the area should be slightly larger than the length or width of mesh, should be the same thickness of about 2mm, except for those requirements Hemming, the polymer mortar does not allow coated polystyrene plate side.

12. After scraped mortar, should net disposed thereon, the curved surface mesh toward the wall, from the center to the surrounding flat trowel applied, so that the mesh embedded in a polymer mortar, mesh should not be wrinkled, until the surface after dry, then wipe on which the application of a layer of polymer mortar, the thickness of 1.0mm, the mesh should not be exposed.

13. Mesh surrounding the lap length not less than 70mm, the severed parts should be used, mending their nets lap, lap length of not less than 70mm.

14. Doors and windows should be done to strengthen the bladder surrounding layer, reinforcing layer mesh attached to the innermost. If the door frame and the skin from the surface of the primary wall is greater than 50mm, mesh and base course wall pasted. If less than 50mm to be done to turn the packet processing. Great wall laying Mesh should be embedded in cement outside of the door frames.

15. Door window at the four corners, the standard network for wiping exhausted, and then the door window corners capped a 200mm × 300mm standard network, the window angle bisector 90 degree angle, attached to the outermost, to strengthen; in the shade angle capped at a length of 200mm, width of bladder suitable window width standard mesh, attached to the outermost.

16. Floor windowsill or less, in order to prevent damage caused by the impact, should be placed reinforced mesh, resettlement standard mesh. Strengthening Mesh response received.

17. The method of construction and placement of reinforcing layer standard mesh identical.

18. Wall pasted mesh should be covered in a mesh bag on the turn.

19. Mesh top-down applied to wiping, simultaneous construction Sincere wipe reinforced mesh, then a standard mesh

20. After the sticky mesh should prevent rain erosion or impact, easy sun angle collision, the doors and windows should take protective measures to be taken on the part of the discharge port pollution prevention measures, the occurrence of surface damage or contamination must be dealt with immediately.

21. After the construction of the protective layer can not be exposed to rain within 4 hours.

22. Shall not be less than 72 hours after the protective layer is not less than the final setting timely water conservation, day and night average temperature higher than 15 ℃ 48 hours, less than 15 ℃.